This is the checklist I run before any equipment order leaves the building — forklifts, mini excavators, skid steer loaders, small tractors, the whole line. It exists because of two orders I got wrong: one in September 2022, one in March 2023. Together they cost about $4,180 in rework, return freight, and one genuinely uncomfortable phone call.

Nine steps. Maybe 90 minutes of real work, assuming you have the spec sheets and a tape measure in front of you. It's written for whoever signs the purchase order — a dealer buying for stock, a contractor replacing a worn-out machine, a farm buyer adding a second tractor. Not the operator.

If you've ever opened a container and found out the machine won't go through your customer's 2.1 m gate, you already know why this exists.

The 9-step checklist

Step 1: Write down the job, not the machine name

Before you open a single spec sheet, write four things in plain language: what the machine lifts or digs, how high or how deep, how wide the tightest gap on site is, and what surface it runs on.

Sounds obvious. It's the step people skip, and it's where the expensive errors start. 'We need a forklift' becomes a 3-ton diesel unit, which becomes a machine 200 mm too wide for the aisle it actually works in. Put those four numbers in the email, not in your head — heads forget, email threads get forwarded to the factory.

Step 2: On a forklift, capacity is a curve — read the data plate

Rated capacity is quoted at a specific load centre, normally 24 inches (600 mm). Move the load out and the number drops fast. A 3,000 lb machine that's fine at a 24-inch load centre is closer to a 2,000 lb machine at 36 inches. The quick math is capacity × (rated load centre ÷ actual load centre), but don't trust my arithmetic — read the plate on the actual unit. ANSI/ITSDF B56.1 sits behind those ratings, and OSHA 29 CFR 1910.178 requires that plate to be legible and the operator trained. If the plate is missing or painted over, that alone is a reason to slow down.

While you're at it: mast type and collapsed height against your door height, fork length, whether a sideshifter is fitted (it eats capacity and adds carriage thickness), and turning radius against aisle width.

The assumption I got wrong was that 'same as the last order' meant the same spec. It didn't. Mast was 300 mm taller. Different container plan, different freight cost, one annoyed customer.

Step 3: Diesel or electric forklift — decide on shift pattern first, power supply second

A diesel forklift makes sense for two or three shifts, outdoor yards, rough or wet surfaces, and sites where fuel is cheap and available locally. Trade-offs are noise, exhaust, and ventilation if it ever goes indoors.

An electric forklift makes sense indoors, in cold storage, food and pharma, anywhere exhaust is a problem. Here's the part buyers miss: the decision isn't really about the machine, it's about the building. Check the voltage (48V and 80V are common), whether you have the 3-phase supply a high-frequency charger needs, charge time (a full shift charge on lead-acid is typically around 8 hours), battery bay space, floor loading, and lead-acid versus lithium. Lithium changes the opportunity-charging math and the invoice.

My mistake here: quoted an electric forklift to a yard with single-phase power and no room for a battery bay. The customer found out at commissioning. We paid freight both ways.

On emissions — EPA Tier 4 Final and EU Stage V are the standards that apply to non-road engines in those markets. Ask which engine model the machine carries and for the document that goes with it. 'It's compliant' is not a document.

Step 4: Match the excavator class to the trench, and check the coupler standard

Digging depth and width should pick the class, not tonnage on a brochure. A mini excavator in the 1–2 t range covers utility work, landscaping and tight residential jobs. A small excavator at 3–5 t is the step up for heavier trenching, demolition buckets and bigger spoil volumes. Above that you're into general construction, which is a different buying conversation.

Two things to verify beyond the spec sheet:

  • Zero-tail or reduced-tail swing. Matters more than maximum reach if the machine works against walls, fences or in a traffic lane.
  • Quick coupler standard and pin dimensions. Pin-on, mechanical or hydraulic — and which pin size. This is the one that bites, because attachments that fit one coupler often don't fit the next, and 'universal' is a word, not a measurement.

Step 5: On a skid steer loader, check hydraulic flow before anything else

This is the step almost everyone skips, and it's the one that turns a good machine into a disappointing one.

A skid steer loader's real usefulness is decided by auxiliary hydraulic flow. Standard flow on a full-size machine often lands around 60–75 L/min; high-flow options push past 110 L/min. Mini skid loaders are lower — frequently under 40 L/min. If the plan involves an auger, breaker, trencher or cold planer, that number decides whether the attachment performs or just spins slowly. Ask for flow in litres per minute at a stated engine RPM, in writing, and ask whether the machine is plumbed for high flow or just 'high-flow ready'.

While you're there: rated operating capacity. Sellers quote it at different percentages of tipping load, so ask which basis the figure uses. Then track versus wheel, and ground pressure if it works on finished lawns or soft ground.

Step 6: On a small tractor, compare at the PTO and compare landed cost — not tractor price

Engine horsepower sells tractors; PTO horsepower does the work. The gap between the two is typically 10–20%. On a compact utility tractor, check PTO rating at 540 rpm, three-point hitch category (Category I is the usual small-tractor setup), lift capacity measured 24 inches behind the link ends, hydraulic flow, and tyre options for your ground.

With tractors for sale listings, the advertised tractor price is almost never the landed number. Add freight, duties, attachment package, a loader if you need one, and the first service kit. I won't publish ranges here — they move every quarter and depend heavily on configuration — so get quotes with an identical spec sheet attached and compare totals. Two quotes with different tyre packages are not comparable, even when the headline numbers look 15% apart.

Step 7: Get dimensions, weight and the loading plan in writing

Ask for these measured, not copied from a brochure: transport length, width, height, operating weight (ISO 6016 covers how machine mass is measured), lifting points, lashing points, and who is responsible for lashing. For container shipments, demand a loading plan. A 40HQ gives you roughly 12.03 m of internal length and about 2.35 m of usable width, and a machine with the ROPS folded versus raised is two different loading problems.

My 2022 error was exactly this. The dimension I quoted came from a drawing with the ROPS folded; the customer's spec assumed it raised. The unit fit the container fine. It didn't fit the customer's shed.

Step 8: Ask for documents, then check the model number on them

Request the user manual in the target language, a nameplate photo, the engine emission document, and any conformity documentation for the market you're selling into. Then do the boring part: confirm the model and serial on every document match the machine you're buying.

A conformity mark on a sticker proves nothing by itself. The document has to name the model. If a supplier can't produce that, treat it as an open question rather than a yes.

Then set the pre-shipment proof pack. Non-negotiable:

  1. Photos of the actual unit, with the serial plate visible in the same frame.
  2. A cold-start video shot outdoors, hour meter readable.
  3. Tape-measure photos of the three dimensions you care about most.
  4. The spare parts list with part numbers, not descriptions.

Step 9: Test the after-sales path before you need it

Send a parts question before you pay the balance, and time the reply. Put four questions in the same email: who pays freight on a warranty part, what the typical lead time is into your country, what is explicitly excluded (wear parts usually are), and who diagnoses the fault — you, a local dealer, or a video call with the factory.

The quality of that answer tells you more than any brochure. We didn't have a formal process for it until the third time a customer asked about a hydraulic hose and got four different answers from four people. Now there's one page, one owner, one stated response window.

The mistakes that keep showing up

  • Quoting capacity without naming a load centre. Most common, most expensive.
  • Buying electric on price, then discovering the building can't charge it.
  • Assuming attachment couplers are interchangeable. They aren't, and 'standard' varies.
  • Skipping hydraulic flow on a skid steer loader order, then wondering why the auger stalls in clay.
  • Comparing tractor price instead of landed cost. Different tyre packages, different totals.
  • Accepting photos of 'a unit like yours' instead of the serial number on your unit.

Where we're not the right supplier

Two honest boundaries, because they save everyone a month.

If you need a 20-tonne-plus excavator, or a national rental fleet with telematics integration and guaranteed same-week parts across multiple depots, we're not the fit. Compact equipment is what we build and ship. A large-line dealer with local stock will serve that requirement better than a factory-direct order, and I'll say so on the call.

A supplier who tells you where their range ends is telling you something useful about the rest of it. The vendor who once said 'this isn't our strength, here's who does it better' earned every order I placed after that. The one who said yes to everything cost me six weeks and a lot of explaining.

Two lines for your purchase order

If you take nothing else: put the load centre, the hydraulic flow, and the three shipping dimensions on the PO itself. Not in an email thread, not in a messaging app — on the document both sides sign. Half the disputes I've dealt with were specification drift, not defective machines. Nobody was lying; nobody wrote it down.

And build the checklist before your first mistake, not after your third. Mine took two.